| | INSPECTION FEES    
| Water Plumbing Inspection Fee | $90.00 | Rough-In Inspection - before slab is poured CSI: Type of lines, cross connections, lead solder/flux Size of Lines Fittings on pex pipe need to be sleeved, no couplings under slab
| | Water Line Inspection CSI: Type of lines, Cross Connections Courtesy Valve installed, Property ties to meter, size of lines, depth of line
| | Customer Service Inspection (CSI) Final
| |
| Sewer Plumbing Inspection Fee | $30.00 | Rough-In Inspection-before slab is poured
| | Sewer Final Inspection
| |
| Grinder Pump Plumbing Inspection Fee | $40.00 | Grinder Pump Inspection Receive Plumbing and Electrical Checklist Verify tank, sewer line, and electrical panel installations
| | Grinder Pump Set
| |
Miscellaneous Charges | Re Inspection Fee | $30.00 | | Backflow Annual Testing Fee | $20.00 |
2006 Uniform Plumbing Codewas adopted on 09-17-2007 byResolution 07-09-088 Effective October 1, 2007 |